Projects
King Hall Renovation |
|
![]() |
Air Handling Units were lifted up via crane to the top of King to be installed the 4th week of April 2006. The new chiller was installed as well two weeks earlier. |
| Images of King Hall Renovation | |
Armfield Athletic Center Renovation |
|
![]() |
The Armfield Press Box had the windows installed during the last week of June and first week of July. The existing bleachers were repaired and updated the first week of August. Carpet was being installed starting the second week of July. The new stadium seating work has begun as well. |
| Images of Armfield Athletic Center Renovation Floor plans and elevations of this project |
|
Founders |
|
![]() |
Ceramic flooring is finished. Painting and lighting have started. The ceiling is completed, lighting going in now. |
| Click here for the Summer Projects Schedule. | |


