Projects

King Hall Renovation
Started: January 2006
Scheduled for completion: Summer 2006

Air Handling Units were lifted up via crane to the top of King to be installed the 4th week of April 2006. The new chiller was installed as well two weeks earlier.

Images of King Hall Renovation

Armfield Athletic Center Renovation
Started: February 2006
Scheduled for completion: Summer 2006

The Armfield Press Box had the windows installed during the last week of June and first week of July. The existing bleachers were repaired and updated the first week of August. Carpet was being installed starting the second week of July. The new stadium seating work has begun as well.

Images of Armfield Athletic Center Renovation
Floor plans and elevations of this project

Founders
Started: May 2006
Scheduled for completion: June 2006

Ceramic flooring is finished. Painting and lighting have started. The ceiling is completed, lighting going in now.

Click here for the Summer Projects Schedule.